Air Quality Permitting

AIR QUALITY PERMITTING
May 2015

WEF Residuals and Biosolids Committee,
Bioenergy Technology Subcommittee,
Combined Heat and Power Working Group

 

For additional Biosolids information, please see biosolids.org.

CONTACT:
Water Environment Federation
601 Wythe Street Alexandria, VA 22314
703-684-2400
email: biosolids@wef.org

Copyright © 2015 Water Environment Federation. All rights reserved.

Acknowledgments


Acknowledgments

Principal Authors

Donald C Trueblood, Managing Scientist, Brown and Caldwell
Lynnette Gerbert, Principal Toxicologist, Brown and Caldwell
Myron Bachman, Plant Superintendent, North Davis Sewer District


Final Reviewers

Kevin R. Cowan, P.E., District Manager, North Davis Sewer District
Sarah A. Deslauriers, P.E., Carollo Engineers, Inc.
Matthew T. Goss, P.E., Technical Strategy Leader – Energy, CDM Smith
Jason Wiser, P.E., Brown and Caldwell

Water Environment Federation
Residuals and Biosolids Committee
Bioenergy Technology Subcommittee

John Willis, P.E., BCEE, Vice President, Brown and Caldwell (Subcommittee Chair)
Dru Whitlock, P.E., Principal Technologist, CH2M Hill (Subcommittee Vice Chair)

 

Copyright © 2015 Water Environment Federation. All rights reserved.

Summary

Air permitting is a challenging task encountered when installing a Combined Heat and Power (CHP) system. One of the foremost reasons is that there is little consistency in how to accomplish it, or what will be required. In addition, the Federal Clean Air Act is one of the most complicated components of the Code of Federal Regulations. Each state is allowed discretion for air quality in their jurisdiction, as long as their regulations are as stringent as the federal ones. Some states have chosen to promulgate regulations that are substantially more stringent than the federal standards. Also some states have not only passed such stringent state programs, but have also divided their state into subdivisions, each with different requirements. An example of this is California, which is divided into 35 air districts, each of which has its own regulations. The California air district requirements are different enough from each other that they are often unrecognizable as having come from the same state.

In addition, terminology can vary among the different agencies. To some, the initial permit is a “Permit to Construct,” for others an “Authority to Construct,” and for others an “Approval Order,” etc. Some agencies use the term Volatile Organic Compounds (VOC) to describe the organic gases that act as precursors to ozone formation in the atmosphere, other agencies call them Non-Methane Hydrocarbons(NMHC), and others, Precursor Organic Compounds(POC). Innumerable examples of terminology confusion exist. This document uses the terms that are most commonly encountered across the country. The application of the appropriate terms within a particular agency may be confusing at first, but once the concepts are clear, the terminology will follow.

 

Copyright © 2015 Water Environment Federation. All rights reserved.

Air Quality Requirements

Air quality requirements can be divided into three categories: Administrative, Performance Standards, and Permitting. Each is independently applicable and an exemption from one is not necessarily an exemption from all.

  1. Administrative requirements include such topics as enforcement procedures, organizational structure and procedures, etc. They are always applicable and will not be discussed further in this fact sheet.
  2. Performance Standards include local requirements which may also be called “prohibitory rules” as well as the Federal New Source Performance Standards (NSPS) and the National Emission Standards for Hazardous Air Pollutants (NESHAP). These requirements apply to certain types of facilities, equipment, or processes regardless of their permitting status. Applicability is quite variable, and some requirements apply regardless of when a source was installed and some apply only to sources installed after a certain date. Some requirements impose more stringent requirements on existing sources and some existing sources are not required to comply with revised limitations. Some requirements apply to sources at facilities that are classified as Major Sources and some apply to sources regardless of the facility categorization. The requirements may also specify emission limits, equipment configuration, fuel specifications, etc.
  3. Permitting requirements generally require a permit application to be submitted and approved by the agency prior to beginning construction of an air emissions source. Permits can be categorized by facility emission levels:



 

Copyright © 2015 Water Environment Federation. All rights reserved.

Air Permitting Process

At a high level, the process of acquiring an air permit is nearly the same in all jurisdictions. Generally, a permit application must be prepared and submitted, it is reviewed by the permitting agency, and in some cases, it requires review by the public. Following all reviews, a permit is either granted or denied. In many jurisdictions, a temporary permit is granted that authorizes construction. After construction is complete and the facility is assured to function as permitted, a final permit is issued.

An important consideration when beginning a permitting process is development of a permitting strategy. This strategy should consider all aspects of the permitting process as described in more detail below. One of the most important elements, however, is agency interaction. The ultimate goals of agency interaction are to make the permitting process move as smoothly as possible and to minimize the number of requirements imposed on the permit. It is important to consider what opportunities are available for agency interaction, the specific goals of each interaction, and how to approach the agency, both generally and specifically at each interaction.

 

Copyright © 2015 Water Environment Federation. All rights reserved.

Permit Application

Applications for a permit, while variable across local agencies, contain common sections:


 

Copyright © 2015 Water Environment Federation. All rights reserved.

Post Application Submittal

Once the application is submitted, the focus of the permitting process shifts to the agency. It is the agency’s responsibility to review and either approve or deny the permit. In some jurisdictions, a public review period is also required. Finally, a few jurisdictions have a requirement to complete an environmental impact review before issuing a permit. However, that aspect of the process is not discussed herein.

Agency review – The agency may perform two types of reviews: completeness and technical. A completeness review, where it is performed, is for the sole purpose of determining whether or not all information is contained in the permit application that the agency will need to make a decision on the application. Completeness reviews are most common where the agency has a statutory limit on the amount of review time that they are allowed. In that case, the completeness review will be outside that time limit. If information is lacking, it will be requested. If not, the agency will deem the application completed and move into the technical review phase. In a technical review, the agency is assessing whether the sources being proposed meet applicable regulatory limitations and determine what additional limitations should be imposed as permit conditions in order to assure that the sources are operated in the manner described in the application. The result of the agency review is usually an engineering analysis and recommendation either to issue the permit, with or without certain conditions, or to deny the permit. At that point, the agency management may take action on the application if public review is not required, or submit the application and analysis for public review if required.

Public review – Public review is ordinarily required when members of the public could be directly impacted by a project, although some jurisdictions have general requirements for public review. A public notification is made, usually by publishing a notice in a local paper and often supplemented with email notifications to agency mailing lists. Occasionally, notice is more direct with mailings to each address in the area. When a public school is located in the zone of potential impact, notices are sometimes sent home with students. The public is given a set period of time to review (usually 30 days, occasionally 60 days) and submit comments if they wish. Not commenting is interpreted as approval. After the comment period has closed, the agency will review the comments that they have received and will take one of three actions: approve the permit as originally recommended, issue a modified permit, or deny the permit, unless it is a Title V permit or another type of permit requiring EPA review.

EPA review – EPA must be given the opportunity to review all Title V permits. In addition, some state programs provide for EPA review of other types of air permits. PSD permits in particular are almost always reviewed by EPA. In fact, many state programs exclude PSD permits from the program, in which case, they must be issued by EPA. EPA’s permitting program is very similar to that described herein, although the requirements for a PSD permit are much more stringent and complex than for other permits.


 